Pisco water supply rehabilitation project

Proyecto terminado

Switzerland supports in partnership with the German Development Bank KfW the restoration of the water supply system in the Peruvian cities of Pisco and San Andrés.

Región/País Período Presupuesto
Perú
01.10.2009 - 31.12.2016
CHF  2’700’000
Contexto

A devastating earthquake of a magnitude 7.9 hit Peru's central coast on August 15th 2007 causing substantial damage to the water and sanitation distribution network in the province of Pisco. Follwoing the international appeal made by the national government together with the Pisco water utility (EMAPISCO) in the afermath of the earthquake, both Switzerland through SECO and Germany through KfW have decided to support the rehabilitation and reconstruction efforts in the most heavily affected towns of Pisco and San Andres in the water supply sector.

Objetivos

Overall goal of the Project is to restore safe and sustainable water supply services to the approx. 90'000 inhabitants of Pisco and San Andrés. Measures under the project focus on the rehabilitation of the principal drinking water network as well as on the improvement of the operation and maintenance of the network. The Project complements efforts of the Peruvian Government in the rehabilitation of the distribution network.

Efectos a medio plazo

Reliable supply of safe drinking water to the population in the service area of EMAPISCO

Improved operation and maintenance of the water supply system

Resultados

Resultados previstos:  

Reconstruction of the drinking water transmission pipeline and principal distribution network in Pisco and San Andres

Improvement and enlargement of a drinking water reservoir (2?300 m3), including comprehensive rehabilitation of/ additions to the hydraulic installation and control system, man-holes, bulk meters and connections.

Procurement of hydrojet for an improved maintenance of the sewer network

Consulting services for design works, tendering support and implementation supervision

Technical assistance for the installation of water meters and sanitary education


Dirección / Officina Federal responsable SECO
Crédito Cooperación al desarrollo
Contrapartes del proyecto Contraparte del contrato
  • KfW banking group


Presupuesto Fase en curso Presupuesto suizo CHF    2’700’000 Presupuesto actual suizo ya emitido CHF    0 Presupuesto inclusive contrapartes del proyecto CHF    6’300’000
Fases del proyecto

Fase 1 01.10.2009 - 31.12.2016   (Completed)