Armenia SET Floods June 2024


Due to heavy rainfall since 25./26.05.2024, severe flooding occurred in two regions of Armenia, which caused some casualties and serious damage to infrastructural facilities such as bridges, roads, railroad lines, pump stations etc. The Armenian authorities asked for international support and accepted Switzerland’s offer for assistance through the deployment of a “SofortEinsatzTeam / SET”, specialized in carrying out structural assessments of damaged infrastructure. Decisions on optimum use of funds will be taken by the Crisis Cell chaired by the Head of HA in close coordination with the desk and Swiss representation in the country.

Land/Region Thema Periode Budget
Armenien
Humanitäre Hilfe & DRR
Humanitäre Effizienz
03.06.2024 - 30.06.2024
CHF  100’000
Hintergrund Two regions in Armenia (Lori and Tavush), which were mainly affected by the flooding
Ziele The Armenian authorities in charge of the disaster response are supported in coping with the consequences of the flooding
Zielgruppen

Directly: Armenian authorities / National Agency of Emergency Management (NEMA), namely the Ministry of Territorial Administration and Infrastructure

Indirectly: Population in Armenia affected by the flooding, having lost or at risk of losing livelihood or infrastructure and lives

Mittelfristige Wirkungen Contribution to the response activities of the Armenian authorities in charge, through engineering expertise to evaluate the infrastructure damaged by the flooding, such as brigdes, roads, railroad lines, pump stations etc.
Resultate

Erwartete Resultate:   Assessment missions in the affected regions and evaluation of damaged infrastructre as well as definition of possible action lines for the recovery phase


Verantwortliche Direktion/Bundesamt DEZA
Projektpartner Vertragspartner
  • Schweizerisches Arbeiterhilfswerk


Budget Laufende Phase Schweizer Beitrag CHF    100’000 Bereits ausgegebenes Schweizer Budget CHF    16’604 Projekttotal seit Anfangsphase Schweizer Beitrag CHF   0 Budget inklusive Projektpartner CHF   500’000
Projektphasen Phase 2 08.07.2024 - 31.12.2025   (Laufende Phase)

Phase 1 03.06.2024 - 30.06.2024   (Active)