Armenia SET Floods June 2024
Due to heavy rainfall since 25./26.05.2024, severe flooding occurred in two regions of Armenia, which caused some casualties and serious damage to infrastructural facilities such as bridges, roads, railroad lines, pump stations etc. The Armenian authorities asked for international support and accepted Switzerland’s offer for assistance through the deployment of a “SofortEinsatzTeam / SET”, specialized in carrying out structural assessments of damaged infrastructure. Decisions on optimum use of funds will be taken by the Crisis Cell chaired by the Head of HA in close coordination with the desk and Swiss representation in the country.
Land/Region | Thema | Periode | Budget |
---|---|---|---|
Armenien |
Humanitäre Hilfe & DRR
Humanitäre Effizienz
|
03.06.2024
- 30.06.2024 |
CHF 100’000
|
- Schweizerisches Korps für humanitäre Hilfe
-
Sektor nach Kategorisierung des Entwicklungshilfeekomitees der OECD NOTHILFE
Sub-Sektor nach Kategorisierung des Entwicklungshilfeekomitees der OECD Koordinierung von humanitärer Hilfe
Unterstützungsform Eigenes Programm der DEZA
Projektnummer 7F11421
Hintergrund | Two regions in Armenia (Lori and Tavush), which were mainly affected by the flooding |
Ziele | The Armenian authorities in charge of the disaster response are supported in coping with the consequences of the flooding |
Zielgruppen |
Directly: Armenian authorities / National Agency of Emergency Management (NEMA), namely the Ministry of Territorial Administration and Infrastructure Indirectly: Population in Armenia affected by the flooding, having lost or at risk of losing livelihood or infrastructure and lives |
Mittelfristige Wirkungen | Contribution to the response activities of the Armenian authorities in charge, through engineering expertise to evaluate the infrastructure damaged by the flooding, such as brigdes, roads, railroad lines, pump stations etc. |
Resultate |
Erwartete Resultate: Assessment missions in the affected regions and evaluation of damaged infrastructre as well as definition of possible action lines for the recovery phase |
Verantwortliche Direktion/Bundesamt |
DEZA |
Projektpartner |
Vertragspartner |
Budget | Laufende Phase Schweizer Beitrag CHF 100’000 Bereits ausgegebenes Schweizer Budget CHF 17’538 Projekttotal seit Anfangsphase Schweizer Beitrag CHF 0 Budget inklusive Projektpartner CHF 500’000 |
Projektphasen |
Phase
2
08.07.2024
- 31.12.2025
(Laufende Phase)
Phase 1 03.06.2024 - 30.06.2024 (Active) |